Gantt chart: critical path
The longest chain of dependent tasks in a project. It sets the shortest possible finish time, and any delay to a task on it delays the whole project. Tasks off it have float.
Understanding Gantt chart: critical path in VCE Software Development U3O2
What it does: The longer path (9 days) controls the finish time, so it is the critical path and the project cannot finish sooner than 9 days. Critical tasks have no float, so any delay to one pushes back every task after it and the project end date. The shortest chain would finish early and does not control the end date. It should say longest chain (9 days).
Common mistakes: Build cannot depend on Test, because Test comes after Build and this would create a loop. Build should start after A, so the line is 'B Build 4d after A'. The critical path A,B,D is only valid with correct dependencies. The critical path is the longest chain of dependent tasks, not the shortest. Path 1 takes 8 days, so it is the critical path.
Free printable worksheet with full answer key — or add this module to a class and your students practise it interactively.
This module's key terms are also in a printable crossword (Modules 12–24) and word search (Modules 2–24).
Take this worksheet further — free with Cloodit
Each concept is reinforced from every angle — learned, then applied, then tested.
Cloodit turns curriculum-aligned coding content into journeys students work through one biome at a time.
Over 100 of them, across seven natural biomes.
Turns their work into revision material ready for Flash Cards and Exam study.
Live, competitive practice for the start of the lesson or a teacher-led lesson finisher.
Honour your top performers, or encourage a student who's trying hard — ready to print in seconds.
Quick Questions
Match the Pairs
Key Term
critical pathFill in the Blanks
Spot the Error
Student with a class code? Join your class →