Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task B: duration 3 days → 5 days | AMoving a dependent task's start date because the task before it finished later | |
| 2Task C start: 10 Mar → 14 Mar | BThe duration was changed to the number of days late instead of the new total. If Testing was planned for 4 days, it should now be 6 days. | |
| 3When a task finishes earlier than planned, its duration is shortened and later tasks can start sooner | CFinal report due: 28 Mar → 2 Apr | |
| 4When a delay pushes work past a deadline, a new deadline is set for the final task | DTesting: duration 5 days → 3 days; Evaluation start 20 Mar → 18 Mar | |
| 5Design: duration 4 days → 6 days (Coding start date left at 12 Mar) | EExtending a duration because the work is taking longer than planned | |
| 6Testing finished 2 days late, so Testing duration changed to 2 days | FThe dependent task was not moved. Coding depends on Design, so its start date must move later to match the longer duration. |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
Adjusting time frames — Changing a task's start date or duration when work takes longer or shorter than planned, then moving any dependent tasks and deadlines to match.duration = 5
duration = duration + 2end = start + duration
print(end)delay = 3
testStart += delaydelay = actualDays - plannedDays
newDeadline = deadline + delayif actualDays > plannedDays:
deadline += delay