Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Add task: Write user guide (2 days, Sam) | ATasks were added without adjusting time frames or reassigning people, so the plan is no longer realistic. | |
| 2Reassign task: Test login (Mia -> Jo) | BAn existing task is given to a different team member so the work can still be completed on time | |
| 3Removing a task that is no longer needed keeps the plan realistic and frees up time and people | CMove task: Design database before Code login page | |
| 4Tasks can be reordered so a delayed task no longer holds up work that depends on it | DThe plan was not adjusted. Tasks should be reassigned to other team members so the work still gets done. | |
| 5Team member leaves -> keep the plan unchanged and hope the tasks get done | ERemove task: Build reports page (client dropped feature) | |
| 6Scope grows by 3 features -> add the tasks but leave all deadlines as they are | FA new task is added to the plan because a need was found that the original plan did not cover |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
adjusting tasks — Changing a project plan's tasks by adding, removing, reordering or reassigning them when circumstances change, so the plan stays realistic and the project stays on track.plan.append("Add login screen")plan.remove("Write help page")owner = {"Test login": "Sam"}
owner["Test login"] = "Mia"plan.insert(0, "Fix login bug")if "Docs" in plan:
plan.remove("Docs")