Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Milestone: Prototype finished - 14 Aug | AA milestone is a checkpoint showing finished work, not a task with a duration. It should say what is complete, for example 'Logo approved - 12 Aug'. | |
| 2Milestone ◆ on Gantt chart | BA diamond marker placed on the timeline where a major piece of work should be finished | |
| 3Setting a milestone date: work backwards from the final deadline so each checkpoint is realistic | CA checkpoint with a set date showing a major piece of work is complete | |
| 4Checking progress against milestones: compare today's status with the planned milestone date | DThe milestone has no deadline, so the team cannot check whether they are on track. Add a date, such as 'Prototype finished - 14 Aug'. | |
| 5Milestone: Design the logo (3 days) | EMilestone: Prototype - due 2 Oct Today: 5 Oct Status: Behind by 3 days | |
| 6Milestone: Prototype finished - (no date) | FFinal deadline: 30 Oct Testing done: 16 Oct Prototype done: 2 Oct |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
milestone — A marked checkpoint in a project plan, such as a finished prototype, showing a major piece of work is complete by its deadline. Used to check progress.MILESTONE "Prototype finished" DUE 14/06MILESTONE "Prototype finished" DUE 14/06MILESTONE "Prototype done" DURATION 0IF done = FALSE AND today > dueDate THENIF prototypeDone = TRUE THEN