Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Design screens: 3 days | AWrite login module: 4 days (estimate) | |
| 2Testing: Week 5 to Week 6 | BThe bar covers Weeks 2, 3 and 4, so the time allocation should be 3 weeks, not 1 week. The bar length and the stated duration do not match. | |
| 3Estimating duration: a developer predicts how long a task will take before drawing its bar | CA task allocated 2 weeks, shown as a bar covering two week columns | |
| 4Total project length: the combined bars, from the earliest start to the latest finish, set how long the project runs | DThe units are mixed (days and weeks), so the time allocations cannot be compared or added to find the total project length. Use one unit such as days throughout. | |
| 5Build database: bar spans Week 2 to Week 4, time allocation = 1 week | EA task with a time allocation of 3 days, drawn as a bar that spans 3 days on the timeline | |
| 6Plan: 2 days, Code: 5 weeks, Test: 3 days | FStart: Week 1, Last task ends: Week 8, Total = 8 weeks |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
time allocation — The estimate of how long each task will take, shown on a Gantt chart as the length of its bar. Bars are measured in days or weeks and together set the total project length.Design: 3 days
Build: 5 days
Total = 3 + 5 = 8 daysBar length = task durationTest: 2 weeks
Release: 1 week
Total = 2 + 1 = 3 weeksDuration = end date - start dateScreens: 4
Time per screen: 2 days
Estimate = 4 * 2 = 8 days