Gantt chart: time allocation

Tip: Choose Save as PDF in the print dialog to download. Use A4 paper size.

Gantt chart: time allocation

Name:
Date:
Class:

Quick Questions

Shade in the A or B circle for each question.

1. On a Gantt chart, what does the length of a task's bar show?
A The estimated time allocation for that task
B The importance of the task to the client
2. Which is an example of time allocation for a task?
A Design the user interface: 5 days
B Design the user interface: Sam is responsible
3. A task is estimated to take 10 days and another 5 days. Which bar is longer on the same scale?
A The 10-day task
B The 5-day task
4. Which time unit suits a Gantt chart for a small project with short tasks?
A Years
B Days
5. When estimating how long a task will take, what is the best approach?
A Give every task the same length so the chart looks neat
B Consider the task's complexity and the developer's experience

Match the Pairs

Draw a line connecting each item on the left to its match on the right.

Left columnRight column
1Design screens: 3 days AWrite login module: 4 days (estimate)
2Testing: Week 5 to Week 6 BThe bar covers Weeks 2, 3 and 4, so the time allocation should be 3 weeks, not 1 week. The bar length and the stated duration do not match.
3Estimating duration: a developer predicts how long a task will take before drawing its bar CA task allocated 2 weeks, shown as a bar covering two week columns
4Total project length: the combined bars, from the earliest start to the latest finish, set how long the project runs DThe units are mixed (days and weeks), so the time allocations cannot be compared or added to find the total project length. Use one unit such as days throughout.
5Build database: bar spans Week 2 to Week 4, time allocation = 1 week EA task with a time allocation of 3 days, drawn as a bar that spans 3 days on the timeline
6Plan: 2 days, Code: 5 weeks, Test: 3 days FStart: Week 1, Last task ends: Week 8, Total = 8 weeks

Definitions

time allocation

Fill in the Blanks

Complete each line of code by filling in the missing parts.

1.
Design: 3 days Build: 5 days Total = 3 _ 5 = 8 days
2.
Bar length = task ________
3.
Test: 2 weeks Release: 1 week Total = 2 + 1 = _ weeks
4.
Duration = end date - _____ date
5.
Screens: 4 Time per screen: 2 days Estimate = 4 _ 2 = 8 days

Spot the Error

Shade in the letter of the line that contains an error.

Question 1
A Task A: Design, 3 days
B Task B: Code, 10 dollars
C Task C: Test, 4 days
Question 2
A Design = 5 days
B Build = 8 days
C Total = Design * Build
D OUTPUT Total
Question 3
A task ← 'Testing'
B duration ← 3
C bar_length ← cost
D OUTPUT bar_length
Question 4
A duration ← -5
B start ← 1
C finish ← start + duration - 1
D OUTPUT finish
Question 5
A Task: Write report
B Estimate: 14 weeks
C Bar length: 2 weeks

Answer Key

Gantt chart: time allocation
Section A: Quick Questions
Q1
A — The estimated time allocation for that task
Q2
A — Design the user interface: 5 days
Q3
A — The 10-day task
Q4
B — Days
Q5
B — Consider the task's complexity and the developer's experience
Section B: Match the Pairs
Q1
Design screens: 3 days → A task with a time allocation of 3 days, drawn as a bar that spans 3 days on the timeline
Q2
Testing: Week 5 to Week 6 → A task allocated 2 weeks, shown as a bar covering two week columns
Q3
Estimating duration: a developer predicts how long a task will take before drawing its bar → Write login module: 4 days (estimate)
Q4
Total project length: the combined bars, from the earliest start to the latest finish, set how long the project runs → Start: Week 1, Last task ends: Week 8, Total = 8 weeks
Q5
Build database: bar spans Week 2 to Week 4, time allocation = 1 week → The bar covers Weeks 2, 3 and 4, so the time allocation should be 3 weeks, not 1 week. The bar length and the stated duration do not match.
Q6
Plan: 2 days, Code: 5 weeks, Test: 3 days → The units are mixed (days and weeks), so the time allocations cannot be compared or added to find the total project length. Use one unit such as days throughout.
Section C: Definitions
Q1
time allocation — The estimate of how long each task will take, shown on a Gantt chart as the length of its bar. Bars are measured in days or weeks and together set the total project length.
Section D: Fill in the Blanks
Q1
Design: 3 days Build: 5 days Total = 3 + 5 = 8 days
Q2
Bar length = task duration
Q3
Test: 2 weeks Release: 1 week Total = 2 + 1 = 3 weeks
Q4
Duration = end date - start date
Q5
Screens: 4 Time per screen: 2 days Estimate = 4 * 2 = 8 days
Section E: Spot the Error
Q1
B — Time allocation is measured in days or weeks, not dollars. Dollars measure cost. It should be 'Task B: Code, 10 days'.
Q2
C — Tasks done one after another have their durations added. Multiplying gives a meaningless number. It should be 'Total = Design + Build'.
Q3
C — A bar's length shows the task's estimated duration, not its cost. It should be 'bar_length ← duration'.
Q4
A — A task's estimated duration must be a positive amount of time. A negative duration can't make a bar. It should be 'duration ← 5'.
Q5
B — The bar length must match the estimated duration. A 2 week bar means a 2 week estimate. It should be 'Estimate: 2 weeks'.