Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task B depends on Task A | AThe successor task cannot start until the predecessor task has finished. | |
| 2Finish-to-start (FS) | BTest program (successor of Code program) | |
| 3A dependency arrow on a Gantt chart runs from the predecessor to the successor | CIf one task is a successor, it must be linked to its predecessor by a dependency, so it cannot run at the same time with no arrow. | |
| 4A successor task is the task that has to wait for another task to be complete | DDesign screens ──> Code interface | |
| 5Code interface ──> Design screens (arrow points back to the earlier task) | ETask A is the predecessor and Task B is the successor, so B cannot start or finish until A is complete. | |
| 6Write SRS (predecessor) and Draw context diagram (successor) run at the same time, with no link | FThe arrow is drawn backwards. A dependency arrow should run from the predecessor (Design screens) to the successor (Code interface). |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
dependency — A link between two tasks where one cannot start or finish until the other is complete. The first is the predecessor, the next is the successor. Shown on a Gantt chart by an arrow.Design -> Code Link type: finish-to-startDesign -> Code
Design is the predecessor taskDesign -> Code
Code is the successor taskTask 2 depends on Task 1Dependency arrow: Design -> Code