Gantt chart: sequencing tasks

Tip: Choose Save as PDF in the print dialog to download. Use A4 paper size.

Gantt chart: sequencing tasks

Name:
Date:
Class:

Quick Questions

Shade in the A or B circle for each question.

1. Sequencing on a Gantt chart means...
A Listing tasks alphabetically by name
B Putting tasks in the order they must happen
2. Task B needs Task A to be finished first. Where does B's bar start on the chart?
A At the same start point as A
B After A's bar ends
3. Two tasks do not depend on each other and the team has enough people. How can they be shown?
A As parallel tasks with overlapping bars
B One after the other, with no overlap
4. Which task order makes sense when sequencing a software project?
A Gather requirements, then design, then build
B Build, then design, then gather requirements
5. On a Gantt chart, what does the position of a task's bar tell you?
A When the task starts and ends
B How important the task is

Match the Pairs

Draw a line connecting each item on the left to its match on the right.

Left columnRight column
1Task A: Week 1-2, Task B: Week 3-4 AThe tasks are in the wrong order. Code is written before the design exists, but design must come first and finish before coding starts.
2Task C: Week 1-3, Task D: Week 1-3 BSequential tasks: Task B starts only after Task A finishes, so the bars sit one after the other on the chart.
3A task that depends on another must start after the task it depends on has finished CDesign interface: Week 2-4, Write data dictionary: Week 2-4
4Independent tasks can be placed in parallel to save project time DTask B starts in Week 2 while Task A is still running, so the bars overlap. B depends on A's output and should start in Week 4 after A ends.
5Write code: Week 1-3, Design solution: Week 4-5 ETest software: starts Week 5, after Code software ends Week 4
6Task A: Week 1-3, Task B: Week 2-4 (B needs A's finished output) FParallel tasks: C and D start in the same week and overlap, so they run at the same time.

Definitions

Sequencing

Fill in the Blanks

Complete each line of code by filling in the missing parts.

1.
Design: Day 1-3 Code: Day 4-8 Code starts after ______ ends
2.
Task A: Day 1-4 Task B: Day 1-3 A and B run in ________
3.
Design: start Day 1, end Day 3 Code: start Day _, after Design ends
4.
Plan: Day 1-2 Design: Day 3-5 Plan is sequenced ______ Design
5.
A: Day 1-4, B: Day 1-3 Task C needs A and B done first C starts Day _ at the earliest

Spot the Error

Shade in the letter of the line that contains an error.

Question 1
A Plan: wk 2-1
B Design: wk 3-4 after Plan
C Code: wk 5-8 after Design
Question 2
A Interview: wk 1-2
B Survey: wk 1-2 parallel
C Analyse: wk 1-2 after both
D Report: wk 5 after Analyse
Question 3
A Design: wk 1-2
B Code: wk 3-5 after Design
C Test: wk 6-7 after Code
D Release: wk 5 after Test
Question 4
A Login: wk 3-5
B Reports: wk 6-8 parallel
C Test: wk 6-7 after both
Question 5
A Needs: wk 1-2 after SRS
B SRS: wk 3-4 after Needs
C Design: wk 5-6 after SRS

Answer Key

Gantt chart: sequencing tasks
Section A: Quick Questions
Q1
B — Putting tasks in the order they must happen
Q2
B — After A's bar ends
Q3
A — As parallel tasks with overlapping bars
Q4
A — Gather requirements, then design, then build
Q5
A — When the task starts and ends
Section B: Match the Pairs
Q1
Task A: Week 1-2, Task B: Week 3-4 → Sequential tasks: Task B starts only after Task A finishes, so the bars sit one after the other on the chart.
Q2
Task C: Week 1-3, Task D: Week 1-3 → Parallel tasks: C and D start in the same week and overlap, so they run at the same time.
Q3
A task that depends on another must start after the task it depends on has finished → Test software: starts Week 5, after Code software ends Week 4
Q4
Independent tasks can be placed in parallel to save project time → Design interface: Week 2-4, Write data dictionary: Week 2-4
Q5
Write code: Week 1-3, Design solution: Week 4-5 → The tasks are in the wrong order. Code is written before the design exists, but design must come first and finish before coding starts.
Q6
Task A: Week 1-3, Task B: Week 2-4 (B needs A's finished output) → Task B starts in Week 2 while Task A is still running, so the bars overlap. B depends on A's output and should start in Week 4 after A ends.
Section C: Definitions
Q1
Sequencing — Putting tasks in the order they must happen on a Gantt chart. Tasks that depend on others start after them, while independent tasks can run in parallel (at the same time).
Section D: Fill in the Blanks
Q1
Design: Day 1-3 Code: Day 4-8 Code starts after Design ends
Q2
Task A: Day 1-4 Task B: Day 1-3 A and B run in parallel
Q3
Design: start Day 1, end Day 3 Code: start Day 4, after Design ends
Q4
Plan: Day 1-2 Design: Day 3-5 Plan is sequenced before Design
Q5
A: Day 1-4, B: Day 1-3 Task C needs A and B done first C starts Day 5 at the earliest
Section E: Spot the Error
Q1
A — A task's end position cannot come before its start position on the chart. Plan should run from week 1 to week 2, so the line should be 'Plan: wk 1-2'.
Q2
C — Analyse depends on both the interview and the survey, so it cannot start until they finish. It should start in week 3: 'Analyse: wk 3-4 after both'.
Q3
D — Release depends on Test, which runs until week 7. Starting in week 5 puts it before its predecessor ends. It should start after Test, in week 8.
Q4
B — Parallel tasks run at the same time, so their bars must overlap. Reports should be weeks 3-5, level with Login. Weeks 6-8 would make it a later task, not a parallel one.
Q5
A — The first task has no predecessor, and SRS already depends on Needs. Making Needs wait for SRS creates a circular dependency. The line should be 'Needs: wk 1-2'.