Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task A: Week 1-2, Task B: Week 3-4 | AThe tasks are in the wrong order. Code is written before the design exists, but design must come first and finish before coding starts. | |
| 2Task C: Week 1-3, Task D: Week 1-3 | BSequential tasks: Task B starts only after Task A finishes, so the bars sit one after the other on the chart. | |
| 3A task that depends on another must start after the task it depends on has finished | CDesign interface: Week 2-4, Write data dictionary: Week 2-4 | |
| 4Independent tasks can be placed in parallel to save project time | DTask B starts in Week 2 while Task A is still running, so the bars overlap. B depends on A's output and should start in Week 4 after A ends. | |
| 5Write code: Week 1-3, Design solution: Week 4-5 | ETest software: starts Week 5, after Code software ends Week 4 | |
| 6Task A: Week 1-3, Task B: Week 2-4 (B needs A's finished output) | FParallel tasks: C and D start in the same week and overlap, so they run at the same time. |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
Sequencing — Putting tasks in the order they must happen on a Gantt chart. Tasks that depend on others start after them, while independent tasks can run in parallel (at the same time).Design: Day 1-3
Code: Day 4-8
Code starts after Design endsTask A: Day 1-4
Task B: Day 1-3
A and B run in parallelDesign: start Day 1, end Day 3
Code: start Day 4, after Design endsPlan: Day 1-2
Design: Day 3-5
Plan is sequenced before DesignA: Day 1-4, B: Day 1-3
Task C needs A and B done first
C starts Day 5 at the earliest