Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task: Build login screen | Duration: 3 days | Depends on: Design mock-up | AThe tasks are ordered without considering dependencies. Testing is placed before Coding even though it depends on the code existing. | |
| 2Critical path: A -> C -> E (12 days) | BA task list entry that gives the task a name, an estimated duration and the earlier task it depends on, ready to be turned into a bar on the Gantt chart | |
| 3Adding a dependency: Task C cannot start until Task B has finished (finish-to-start) | CMilestone: Prototype approved | Duration: 0 days | Date: Day 15 | |
| 4Marking a milestone: a zero-duration point showing a key deliverable is complete | DThe longest chain of dependent tasks on the chart, marked to show which tasks cannot be delayed without delaying the whole project | |
| 5Task list: Testing (5 days), Coding (10 days). Chart order: Testing starts Day 1, Coding starts Day 6 | EThe critical path is the longest sequence of dependent tasks, not the shortest task. Tasks with float are not on it. | |
| 6Critical path = the task with the shortest duration on the chart | FTask C | Start: after Task B ends | Depends on: B |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
Gantt chart — A bar chart built by listing tasks, estimating durations, ordering them by dependency, then marking milestones and the critical path on a timeline.Task A: Analyse needs | Duration: 3 daysA: Analyse needs (3 days)
B: Design screens (2 days)
B depends on A: start B after A endsMilestone: Design signed off, 0 daysCritical path = longest chain of tasksPath A-B-D: 3 + 2 + 4 = 9 days
Path A-C-D: 3 + 1 + 4 = 8 days
Critical path: A, B, D