Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task 3: Build charts. Planned 12 May, actual 16 May. Reason: data cleaning ran late. | AAn annotation that records the original date, the actual date and the reason for the change | |
| 2Original bar: 1-12 May (grey). Actual bar: 1-16 May (blue). | BThe original date was overwritten, so the original plan is no longer visible and the size of the change cannot be compared. | |
| 3A good annotation gives the date it was written so the change can be tracked over time | C[8 Jun] Report due date changed to 12 Jun. Reason: client requested extra chart. | |
| 4An annotation must state the reason for the change, not just the new date | D[20 May] Testing moved from 18 May to 22 May. Reason: tester away sick. | |
| 5Task 4: Planned 10 Jun. Deleted and replaced with actual date 14 Jun. | EThe note has no date written and no reason for the change, and it does not show the original date. | |
| 6Task 5: Moved to 20 Jun. | FKeeping the original plan visible next to the actual dates |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
annotation — A short dated note on a project plan that records what changed and why, and keeps the original plan visible next to the actual dates.Task 3: Build dashboard
Original: 10 May | Actual: 14 May
Reason: Data file arrived lateTask 3: Build dashboard
Original: 10 May | Actual: 14 May
Reason: Data file arrived lateTask 3: Build dashboard
Original: 10 May | Actual: 14 May
Reason: Data file arrived lateAnnotation 12 May: Task 3 moved to 14 May
Original: 10 May (still shown)Task 3 delay
Days late: 14 May - 10 May = 4 days