Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task B duration: 3 days → 5 days | AA shorter task may allow later tasks to start earlier and the finish date to be revised, but this was not checked. | |
| 2Task C start: Mon 10 → Wed 12 | BExtending a task because it is taking longer than planned | |
| 3When a task is extended, every task that depends on it may have to start later | COriginal finish: Fri 21 + 2 day delay = Tue 25 (revised finish) | |
| 4Work out the revised finish date by adding the delay to the original finish date | DTask A (+2 days) → Task B start +2 days → Task C start +2 days | |
| 5Task A extended by 3 days. Task B start date left unchanged. | EThe dependent task's start date was not updated, so the plan now shows Task B starting before Task A has finished. | |
| 6Task runs 2 days short. Project finish date stays the same, so no change is needed. | FMoving a dependent task's start date because the task before it finished late |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
Adjust time frames — Update start dates, durations and deadlines when a task runs long or short, then check the knock-on effect on dependent tasks and work out the revised finish date.=B2+C2=D2+1duration ← duration + 3=MAX(D2:D6)newFinish ← oldFinish + delay