Adjusting time frames in a project plan

Tip: Choose Save as PDF in the print dialog to download. Use A4 paper size.

Adjusting time frames in a project plan

Name:
Date:
Class:

Quick Questions

Shade in the A or B circle for each question.

1. A data cleaning task planned for 3 days will take 5 days. What should you update in the project plan?
A Leave the plan as it is and hope the later tasks catch up
B Change the task duration to 5 days and check later tasks
2. Task B cannot start until Task A finishes. Task A is extended by 2 days. What happens to Task B?
A Its start date moves back by 2 days
B Its start date stays the same
3. Which sentence best describes the knock-on effect of extending a task?
A Later tasks that depend on it may be delayed
B Only the extended task is ever affected
4. Task C is independent of the extended Task A and has plenty of float. Does its start date need to change?
A Not necessarily, because it does not depend on Task A
B Yes, every task must move back by the same amount
5. A project was due on 20 June. A task on the critical path is extended by 4 days with no time to catch up. What is the revised finish date?
A 20 June
B 24 June

Match the Pairs

Draw a line connecting each item on the left to its match on the right.

Left columnRight column
1Task B duration: 3 days → 5 days AA shorter task may allow later tasks to start earlier and the finish date to be revised, but this was not checked.
2Task C start: Mon 10 → Wed 12 BExtending a task because it is taking longer than planned
3When a task is extended, every task that depends on it may have to start later COriginal finish: Fri 21 + 2 day delay = Tue 25 (revised finish)
4Work out the revised finish date by adding the delay to the original finish date DTask A (+2 days) → Task B start +2 days → Task C start +2 days
5Task A extended by 3 days. Task B start date left unchanged. EThe dependent task's start date was not updated, so the plan now shows Task B starting before Task A has finished.
6Task runs 2 days short. Project finish date stays the same, so no change is needed. FMoving a dependent task's start date because the task before it finished late

Definitions

Adjust time frames

Fill in the Blanks

Complete each line of code by filling in the missing parts.

1.
=B2+__
2.
=__+1
3.
duration ← duration _ 3
4.
=___(D2:D6)
5.
newFinish ← oldFinish + _____

Spot the Error

Shade in the letter of the line that contains an error.

Question 1
A design_days = 5 - 2
B build_start = design_days + 1
C build_days = 4
D finish = build_start + build_days - 1
Question 2
A design_days = 5
B delay = 2
C design_days = design_days + delay
D build_start = design_days - 1
Question 3
A planned_end = 10
B change = 3
C new_end = planned_end * change
D print(new_end)
Question 4
A test_days = 6
B saved = 2
C test_days = test_days + saved
D print(test_days)
Question 5
A a_days = 3 + 2
B b_days = 4
C c_days = 2
D finish = a_days + c_days

Answer Key

Adjusting time frames in a project plan
Section A: Quick Questions
Q1
B — Change the task duration to 5 days and check later tasks
Q2
A — Its start date moves back by 2 days
Q3
A — Later tasks that depend on it may be delayed
Q4
A — Not necessarily, because it does not depend on Task A
Q5
B — 24 June
Section B: Match the Pairs
Q1
Task B duration: 3 days → 5 days → Extending a task because it is taking longer than planned
Q2
Task C start: Mon 10 → Wed 12 → Moving a dependent task's start date because the task before it finished late
Q3
When a task is extended, every task that depends on it may have to start later → Task A (+2 days) → Task B start +2 days → Task C start +2 days
Q4
Work out the revised finish date by adding the delay to the original finish date → Original finish: Fri 21 + 2 day delay = Tue 25 (revised finish)
Q5
Task A extended by 3 days. Task B start date left unchanged. → The dependent task's start date was not updated, so the plan now shows Task B starting before Task A has finished.
Q6
Task runs 2 days short. Project finish date stays the same, so no change is needed. → A shorter task may allow later tasks to start earlier and the finish date to be revised, but this was not checked.
Section C: Definitions
Q1
Adjust time frames — Update start dates, durations and deadlines when a task runs long or short, then check the knock-on effect on dependent tasks and work out the revised finish date.
Section D: Fill in the Blanks
Q1
=B2+C2
Q2
=D2+1
Q3
duration ← duration + 3
Q4
=MAX(D2:D6)
Q5
newFinish ← oldFinish + delay
Section E: Spot the Error
Q1
A — Design ran 2 days longer than planned, so the extra days must be added (5 + 2), not subtracted. Extending a task increases its duration.
Q2
D — The dependent build task can only start after the extended design task ends, so its start is design_days + 1. Subtracting 1 would make it start before design is finished.
Q3
C — A 3 day extension moves the finish date by adding 3 days to the planned end. Multiplying gives 30, which is not the revised finish date. It should be planned_end + change.
Q4
C — Testing finished 2 days early, so the saved days must be subtracted to shorten the duration. Adding them would wrongly lengthen the task.
Q5
D — The revised finish date must include every dependent task in the chain. Task B was left out, so the knock-on effect is wrong. It should add a_days, b_days and c_days.