Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task bar shaded 60% | AThe shading does not match the real progress. It should be shaded only to about 50% to show actual work completed. | |
| 2Shading ends before today's date line | BThe task is behind schedule (late) because less work is done than the plan required by today | |
| 3Shade the completed part of a task bar so progress can be compared with the planned dates | C60% of the task is complete, so the shaded part of the bar shows the work done so far | |
| 4When the plan changes, adjust the bar and record why in the project log | DThe change to the plan was not recorded. The reason for the adjustment must be written in the project log. | |
| 5Task planned 1-10 Mar, 100% shaded, but work is only half done | ETesting moved to 15-19 Mar | Reason: survey data arrived late | |
| 6Task is late, so the end date is changed on the chart with no note in the log | FDesign task: bar 1-10 Mar, shaded to 5 Mar (50%) |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
Progress shading — Shading the completed part of each task bar on a Gantt chart, then comparing it with the planned dates to see whether the task is on time or late.=D2/C2=IF(AND(E2<TODAY(),F2<1),"Late","On time")IF actualPercent < plannedPercent THEN
status ← "Late"
END IFnewEnd ← oldEnd + delayDays
log ← "Delay: supplier was late"=C2*F2