Kanban boards

Tip: Choose Save as PDF in the print dialog to download. Use A4 paper size.

Kanban boards

Name:
Date:
Class:

Quick Questions

Shade in the A or B circle for each question.

1. On a Kanban board, what does each card represent?
A A single team member's whole job
B A single task in the project
2. Your team has finished designing the logo. Where should that card go?
A Move it to the Done column
B Delete it so the board stays tidy
3. Which set of columns is typical for a simple Kanban board?
A To do, Doing, Done
B Start, Middle, Deadline
4. A team sets a work in progress (WIP) limit of 3 on the Doing column. Three cards are already there. What should happen next?
A Finish a card before pulling in a new one
B Add a fourth card so no one is waiting
5. Why do teams limit work in progress?
A It makes the board look neater for the teacher
B It helps tasks get finished instead of piling up half-done

Match the Pairs

Draw a line connecting each item on the left to its match on the right.

Left columnRight column
1To do | Doing | Done AThe three basic columns of a Kanban board, showing a task's stage from left to right
2Doing (WIP limit: 3) BThe Doing column holds 5 cards, which goes over its limit of 2. The team should finish tasks before starting new ones.
3Each task is written on a card, and the card moves to the next column when its stage is finished CCard: Write survey questions | Assigned to: Mia
4A card is assigned to one person so everyone knows who is responsible for that task DCard: Design logo | moved from Doing to Done
5Doing (WIP limit: 2) has 5 cards EThe card is assigned to everyone, so no single person is clearly responsible. It should be assigned to one named person.
6Card: Build website | Assigned to: Everyone FA column that allows no more than 3 cards at once, so the team finishes work before starting more

Definitions

Kanban board

Fill in the Blanks

Complete each line of code by filling in the missing parts.

1.
Columns: To do | _____ | Done
2.
Doing [___ limit: 3]
3.
Card: Draw wireframe ________: Mia
4.
Card: Test app Move: Doing -> ____
5.
Add card: Write report Column: _____

Spot the Error

Shade in the letter of the line that contains an error.

Question 1
A BOARD Website
B COLUMNS Done | Doing | To do
C CARD Draw logo IN To do
Question 2
A BOARD Quiz App
B COLUMNS To do | Doing | Done
C CARD Write quiz IN To do
D MOVE Write quiz TO Testing
Question 3
A BOARD Game Jam
B COLUMNS To do | Doing | Done
C LIMIT Done 3
D CARD Sprites IN Doing
Question 4
A BOARD Poster
B CARD Draw art IN To do
C ASSIGN Sam TO Draw art
D MOVE Draw art TO Doing
Question 5
A COLUMNS To do | Doing | Done
B LIMIT Doing 1
C CARD Record IN Doing
D CARD Edit IN Doing

Answer Key

Kanban boards
Section A: Quick Questions
Q1
B — A single task in the project
Q2
A — Move it to the Done column
Q3
A — To do, Doing, Done
Q4
A — Finish a card before pulling in a new one
Q5
B — It helps tasks get finished instead of piling up half-done
Section B: Match the Pairs
Q1
To do | Doing | Done → The three basic columns of a Kanban board, showing a task's stage from left to right
Q2
Doing (WIP limit: 3) → A column that allows no more than 3 cards at once, so the team finishes work before starting more
Q3
Each task is written on a card, and the card moves to the next column when its stage is finished → Card: Design logo | moved from Doing to Done
Q4
A card is assigned to one person so everyone knows who is responsible for that task → Card: Write survey questions | Assigned to: Mia
Q5
Doing (WIP limit: 2) has 5 cards → The Doing column holds 5 cards, which goes over its limit of 2. The team should finish tasks before starting new ones.
Q6
Card: Build website | Assigned to: Everyone → The card is assigned to everyone, so no single person is clearly responsible. It should be assigned to one named person.
Section C: Definitions
Q1
Kanban board — A board where each task is a card that moves through columns like To do, Doing and Done, so the whole team can see the project's status at a glance.
Section D: Fill in the Blanks
Q1
Columns: To do | Doing | Done
Q2
Doing [WIP limit: 3]
Q3
Card: Draw wireframe Assigned: Mia
Q4
Card: Test app Move: Doing -> Done
Q5
Add card: Write report Column: To do
Section E: Spot the Error
Q1
B — The columns are in the wrong order. A Kanban board reads left to right, so cards move from To do to Doing to Done. It should be COLUMNS To do | Doing | Done.
Q2
D — The board has no Testing column. A card can only move to a column that exists, so this should be MOVE Write quiz TO Doing.
Q3
C — A work in progress limit goes on the Doing column. Capping Done would stop finished work from piling up, which is not the point. It should be LIMIT Doing 3.
Q4
C — The card and the person are swapped. You assign a card to a person, so it should be ASSIGN Draw art TO Sam.
Q5
B — Two cards are already in Doing, so a limit of 1 is broken straight away. The limit should be 2 to match the work in progress.