Breaking a project into tasks

Tip: Choose Save as PDF in the print dialog to download. Use A4 paper size.

Breaking a project into tasks

Name:
Date:
Class:

Quick Questions

Shade in the A or B circle for each question.

1. Which is a better task for a project to make a class website?
A Write the text for the About page
B Do the website
2. Your team is making a short video. Which order makes sense?
A Write the script, then film the scenes
B Film the scenes, then write the script
3. True or false: a task list should be written in the order the tasks must be done.
A True
B False
4. Which task has a clear outcome?
A Work on the app
B Draw a wireframe of the home screen
5. A task list table has columns for the task, who does it, and how long it will take. Why add an estimated time?
A To make the list look longer
B To help plan how long the whole project will take

Match the Pairs

Draw a line connecting each item on the left to its match on the right.

Left columnRight column
1Task 2 | Write quiz questions | Needs: Task 1 AThe tasks are in the wrong order. You can't present before you build, so Build should come first.
2Task 4 | Test the game | 30 min BTask 1 | Draw the game board on paper | Done: board sketch
3A task with a clear outcome says exactly what will be finished CThe task is too big and has no clear outcome. Break it into smaller steps like 'Sketch the home page' or 'Write the About text'.
4A task list puts small tasks in the order they must be done DA task row with a time estimate: it says how long the task should take
5Task 1 | Make the whole website EA task row with a dependency: Task 2 can only start after Task 1 is finished
6Task 1 | Present the project Task 2 | Build the project F1. Plan 2. Build 3. Test 4. Share

Definitions

task list

Fill in the Blanks

Complete each line of code by filling in the missing parts.

1.
Task 1: Research the topic | 30 min Task _: Write the slides | 45 min Task 3: Practise the talk | 20 min
2.
Task 1: Collect photos | 20 min Task 2: Build the slideshow | 40 min Task 3: Present to class | needs Task _
3.
Task | _______ | Time Sketch poster | Sketch finished | 15 min Add colour | Poster coloured in | 30 min
4.
Task 1: Plan the quiz | 30 min Task 2: Make the quiz | 45 min Total: 30 + 45 = __ min
5.
Task 1: Plan the video | 20 min Task 2: Film the video | _____ Task 1 Task 3: Edit the video | needs Task 2

Spot the Error

Shade in the letter of the line that contains an error.

Question 1
A T1 Do podcast | 2h | none
B T2 Record voices | 1h | T1
C T3 Edit audio | 2h | T2
D T4 Publish episode | 1h | T3
Question 2
A T1 Research topic | 2h | none
B T2 Draft text | 1h | T1
C T3 Choose images | 1h | T1
D T4 Print poster | 1h | none
Question 3
A T1 Pick topic | 20min | none
B T2 Research facts | 2h | T1
C T3 Make 10 slides | 1min | T2
D T4 Practise talk | 1h | T3
Question 4
A T1 Sketch levels | 1h | T3
B T2 Code the game | 3h | T1
C T3 Test the game | 1h | T2
Question 5
A T1 Plan scenes | 1h | none
B T2 Film all scenes | T1
C T3 Edit clips | 2h | T2

Answer Key

Breaking a project into tasks
Section A: Quick Questions
Q1
A — Write the text for the About page
Q2
A — Write the script, then film the scenes
Q3
A — True
Q4
B — Draw a wireframe of the home screen
Q5
B — To help plan how long the whole project will take
Section B: Match the Pairs
Q1
Task 2 | Write quiz questions | Needs: Task 1 → A task row with a dependency: Task 2 can only start after Task 1 is finished
Q2
Task 4 | Test the game | 30 min → A task row with a time estimate: it says how long the task should take
Q3
A task with a clear outcome says exactly what will be finished → Task 1 | Draw the game board on paper | Done: board sketch
Q4
A task list puts small tasks in the order they must be done → 1. Plan 2. Build 3. Test 4. Share
Q5
Task 1 | Make the whole website → The task is too big and has no clear outcome. Break it into smaller steps like 'Sketch the home page' or 'Write the About text'.
Q6
Task 1 | Present the project Task 2 | Build the project → The tasks are in the wrong order. You can't present before you build, so Build should come first.
Section C: Definitions
Q1
task list — A list of small tasks, each with a clear outcome, written in the order they must be done. It breaks a big project into steps you can plan, time and tick off.
Section D: Fill in the Blanks
Q1
Task 1: Research the topic | 30 min Task 2: Write the slides | 45 min Task 3: Practise the talk | 20 min
Q2
Task 1: Collect photos | 20 min Task 2: Build the slideshow | 40 min Task 3: Present to class | needs Task 2
Q3
Task | Outcome | Time Sketch poster | Sketch finished | 15 min Add colour | Poster coloured in | 30 min
Q4
Task 1: Plan the quiz | 30 min Task 2: Make the quiz | 45 min Total: 30 + 45 = 75 min
Q5
Task 1: Plan the video | 20 min Task 2: Film the video | needs Task 1 Task 3: Edit the video | needs Task 2
Section E: Spot the Error
Q1
A — 'Do podcast' is too vague. A task needs a clear outcome you can tick off. It should be something like 'T1 Write script | 2h | none'.}
Q2
D — Printing can't start straight away. It depends on the text (T2) and the images (T3) being finished first. The dependency should be 'T2,T3', not 'none'.
Q3
C — Making 10 slides in 1 minute is not a realistic time estimate. A sensible estimate is about 2h, so the line should read 'T3 Make 10 slides | 2h | T2'.
Q4
A — The first task can't depend on a later task, because T3 can't happen until T1 is done. T1 has nothing before it, so it should say 'none'.
Q5
B — This task has no time estimate. Every task needs one so the plan can be timed. It should read 'T2 Film all scenes | 2h | T1'.