Shade in the A or B circle for each question.
Draw a line connecting each item on the left to its match on the right.
| Left column | Right column | |
|---|---|---|
| 1Task 2 | Write quiz questions | Needs: Task 1 | AThe tasks are in the wrong order. You can't present before you build, so Build should come first. | |
| 2Task 4 | Test the game | 30 min | BTask 1 | Draw the game board on paper | Done: board sketch | |
| 3A task with a clear outcome says exactly what will be finished | CThe task is too big and has no clear outcome. Break it into smaller steps like 'Sketch the home page' or 'Write the About text'. | |
| 4A task list puts small tasks in the order they must be done | DA task row with a time estimate: it says how long the task should take | |
| 5Task 1 | Make the whole website | EA task row with a dependency: Task 2 can only start after Task 1 is finished | |
| 6Task 1 | Present the project Task 2 | Build the project | F1. Plan 2. Build 3. Test 4. Share |
Complete each line of code by filling in the missing parts.
Shade in the letter of the line that contains an error.
task list — A list of small tasks, each with a clear outcome, written in the order they must be done. It breaks a big project into steps you can plan, time and tick off.Task 1: Research the topic | 30 min
Task 2: Write the slides | 45 min
Task 3: Practise the talk | 20 minTask 1: Collect photos | 20 min
Task 2: Build the slideshow | 40 min
Task 3: Present to class | needs Task 2Task | Outcome | Time
Sketch poster | Sketch finished | 15 min
Add colour | Poster coloured in | 30 minTask 1: Plan the quiz | 30 min
Task 2: Make the quiz | 45 min
Total: 30 + 45 = 75 minTask 1: Plan the video | 20 min
Task 2: Film the video | needs Task 1
Task 3: Edit the video | needs Task 2